Operational
Lobito port mineral terminal
LAR-operated minerals terminal; first vessel July 2024, record 50,000 t sulphur vessel January 2026.
Where on the corridor
- Announced
- Study
- Design
- Prequalification
- Bid
- Evaluation
- Award
- Construction
- Operational
- Total value
- —
- Target completion
- —
- Countries
- Angola
- Sector
- Port
<p>Operated under the LAR concession. The MV Lindsaylou docked on 12 July 2024 with 40,500 t of sulphur, beginning port operations; a record 50,000 t bulk sulphur vessel was received in January 2026. Throughput around 10,000 t/month as of 2025–26 field reporting.</p>